66
Bushing Tests
SF6 dead tank circuit breakers occasionally utilize condenser bushings with test
taps which should be routinely tested whenever the overall insulation of the
breaker is tested.
The table supplied may be used to measure the C1 insulation on condenser
bushings, if so equipped. The HV lead is connected to each bushing top
terminal, in turn, and the LV Red lead is connected to the respective bushing test
tap. For all tests, test mode is UST-R. At the completion of each test, the HV
and Red leads are then moved to the next bushing to be tested.
Diagnostic Tests
These tests provide flexibility for performing more diagnostic tests in the event
that an area of concern presents itself. Each test line allows the operator to
choose between test modes UST-R, and GST-GND. A detailed description of
the tests performed should be documented on the form, both in the
Specimen/Connection field and the form Comments field.